Rapid Drawdown Tutorial
1. Introduction
The concept of excess pore pressure using the B-bar method can also be applied to unloading scenarios. If a load is removed quickly from a low permeability material, a “negative excess pore pressure” can be induced.
The change in pore pressure is given by:
where B (B-bar) is the overall pore pressure coefficient for a material. In Slide2, this can be used to simulate the pore pressure changes due to rapid drawdown of ponded water in earth dams.
In the Slide2 Rapid Drawdown (B-bar method) analysis:
1. An initial water table is defined. This defines the initial pore pressure distribution and the initial weight of ponded water.
2. For a complete drawdown scenario, it is assumed that all ponded water is removed from the model. The change in pore pressure for undrained materials is calculated due to the removal (unloading) of the ponded water according to Equation 1. The final pore pressure at any point is the sum of the initial pore pressure and the (negative) excess pore pressure.
3. For a partial drawdown scenario, a drawdown water table is also defined. In this case, the unloading is due to the removal of ponded water to the drawdown level. This determines the change in pore pressure for undrained materials. The pore pressure in drained materials will be calculated from the drawdown water table.
This tutorial will demonstrate rapid drawdown analysis using the B-bar method in Slide2. The following scenarios will be analyzed: full reservoir, complete drawdown, partial drawdown.
The finished file can be found in File > Recent Folders > Tutorials Folder > Tutorial 13 Rapid Drawdown.slmd.
OTHER DRAWDOWN METHODS
See Tutorial 17 for other rapid drawdown methods available in Slide2: • Duncan and Wright 3-stage (1990) • Army Corps 2-stage (1970) • Lowe and Karafiath (1960)
2. Full Reservoir - Steady State
First, we will analyze a dam with a full reservoir.
From the Slide2 main menu, select File > Recent Folders > Tutorials Folder and read in the Tutorial 13 Drawdown1.slmd file. You can rename Group 1 to “Full Reservoir Steady State”.
Dam with full reservoir
The model represents a dam with a clay core, a transition zone, and a granular fill outer layer.
Run Compute and then view the results in Interpret. The critical slip circle has a safety factor = 1.99. Select the Show Slices option to highlight the sliding region.
Critical slip circle with full reservoir
3. Rapid Drawdown of Entire Reservoir
Go back to the Modeler. Duplicate the “Full Reservoir Steady State” group and name the new group “Rapid Drawdown (Entire)”.
In this group, we will simulate a complete drawdown of the reservoir.
PROJECT SETTINGS
1. Select Project Settings > Groundwater
2. Check the Advanced checkbox and specify Rapid Drawdown Method = Effective Stress using B-bar. The change in pore pressure due to removal of the ponded water will be calculated using the B-bar method.
3. Click OK to save the settings.
MATERIAL PROPERTIES
1. Select Properties > Define Materials.
2. For the “clay core”, “transition” and “hard bottom” materials click the Undrained Behaviour checkbox and enter B-bar = 1. This will result in a negative pore pressure change for any of these materials which is located beneath the ponded water, calculated according to Equation 1.
3. The “granular fill” is assumed to be free-draining, so the “undrained” checkbox is NOT selected. For a complete drawdown scenario, this will result in zero final pore pressure for this material.
4. Click OK to save the changes.
Run Compute, and view the results in Interpret. You should see the following critical slip surface (FS = 1.44). Select the Show Slices option
Critical slip surface after rapid drawdown
The critical safety factor after rapid drawdown is significantly lower than the safety factor of the full reservoir, as we would expect, due to the removal of the support provided by the ponded water against the slope. For this example, the critical slip circles, before and after drawdown, are quite similar (i.e. large, deep-seated surfaces passing through the core of the dam).
Let’s examine the pore pressure along this slip surface. Select Graph Query from the toolbar.
Select Pore Pressure as the primary data, and Initial Pore pressure as the secondary data, and select Create Plot. You should see the following plots.
Initial Pore Pressure and Final Pore pressure
Notice that the (final) Pore Pressure is lower than the Initial Pore Pressure for most of the slip surface.
• For the portion of the slip surface within the “transition” material (B-bar = 1) this is due to the negative change in pore pressure due to removal of the ponded water load.
• For the portion of the slip surface within the “granular fill” material (free draining) the final pore pressure is zero due to the complete drainage of the fill material.
Let’s plot the Excess Pore pressure. Right-click on the graph, and select “Change Plot Data” from the popup menu. Select Excess Pore Pressure as the secondary data, and select Create Plot. You should see the following plot.
Final pore pressure and excess pore pressure, rapid drawdown analysis
The negative excess pore pressure is clearly visible on the plot.
• For the portion of the slip surface within the “transition” material (B-bar = 1) this is due to the negative change in pore pressure due to removal of the ponded water load.
• For the “granular fill” material, the “negative excess pore pressure” is actually the change in pore pressure due to the lowering of the water table. Since the granular fill is free draining, the negative excess pore pressure is NOT due to the B-bar unloading effect but is simply the difference between the initial and final pore pressure.
4. Rapid Drawdown to Specified Level
Finally, let’s demonstrate how we can model rapid drawdown to a specified water level, rather than a full drawdown. Duplicate the “Rapid Drawdown (Entire)” group and name the new group “Rapid Drawdown (Specific Level)”. We will be editing this group.
1. Select Boundaries > Add Drawdown Line.
2. In the prompt line enter t then Enter.
3. In the Coordinate Table that appears, copy and paste the following coordinates, then click OK.
X-Coordinate | Y-Coordinate |
0 | 0 |
37.8530642196367 | 7.3830662547644 |
79.292 | 18.543 |
135.398610454628 | 45.5376610208739 |
175.1 | 20 |
265 | 20 |
4. Hit Enter to complete entering the water line.
Partial drawdown of reservoir
Run Compute, and view the results in Interpret.
For this example, the minimum safety factor at partial drawdown (FS = 1.24) is lower than the minimum safety factor at full drawdown. This is due to the material properties and geometry of the slope – e.g. complete drainage (zero pore pressure), assumed for the granular material for the complete drawdown state. At partial drawdown, the drawdown water table creates significant pore pressure in the granular material, towards the toe of the slope, and this leads to the lower safety factor. For this particular model, a minimum safety factor, therefore, exists at some intermediate drawdown level.