Case Study

Evaluating the Efficiency of Room and Pillar Mining in Greece using RS3

Published on: Apr 18, 2023 Updated on: Nov 09, 2023 6 minutes read

Underground mining of unexploited coal reserves is on the rise in Greece, due to its heavy dependency on lignite resources for electricity. The room and pillar approach for underground mining is a conventional method that follows material extractions by creating horizontal arrays of rooms while the pillars remain untouched to support the roof overburden. This method can be economical and effective, but its implementation depends on its stability, which should be evaluated through detailed stress analysis and rock mass characterization.

This study evaluated the feasibility of the room and pillar method for a pilot-scale underground coal mine project in Northern Greece. For a comprehensive 3D numerical analysis, RS3's 3D Finite Element Analysis (FEA) was used. To optimize the design and mining operations, the excavation stages were modeled in RS3 and the stability conditions of the mine were analyzed. The findings were further compared to the actual excavation responses to verify the accuracy of RS3’s 3D modeling and analysis capabilities.

The Unexplored Coal Reservoir Underneath Prosilio Open Pit Mine

The Prosilio mine site in northwestern Greece, consisted of an unexploited reserve that had about a 5.5m thick coal strata layer which was of a good calorific value, and superior in quality to other lignite deposits in the area.

Initially, exploitation of the mine started with an open pit excavation, but to maximize coal extraction and investigate further potential of this underground coal body, the coal deposit extracted directly from the pit bottom seemed like an ideal approach for this project.

The image shows a view of the Prosilio coal mine in Greece
Figure. 1 General view of the Prosilio coal open pit mine

Mine Design: Understanding pillar performance through 3D Finite Element Analysis (FEA)

The aim of this analysis was to evaluate the effectiveness of the room and pillar mine design by analyzing the pillar performance and support requirements using RS3.

When it comes to safe and economical room and pillar mining, defining the right coal pillar dimensions is the key to maintaining stability during excavation. In this case, RS3 was used to accurately capture the strength characteristics of rock mass in the Prosilio exploitation, while providing pillar design recommendations.

Model creation and RS3’s 3D numerical analysis

  • Information on geotechnical properties including coal orebody and the surrounding strata was collected from previous investigation records.
  • The rock mass found in the area consisted of brown coal orebody (5.7 m thick) and marl formation in the hanging wall and footwall.
  • Geotechnical properties (Table 1) selected for this analysis were based on field observations and lab testing of the Prosilio mine.
  • Mohr-Coulomb failure criterion was used to describe the behaviour of both lignite and marl
  • Two primary access tunnels (X1, X2) were designed through which the main part of the pilot mining would be developed.
  • This included two additional galleries (Z1, Z2) parallel to the main access tunnels and four horizontal cross-cuts (Z1, Z2, Z3 and Z4) that eventually developed a total of nine coal pillars (shown in Figure 2.)

Table 1: Rock mass geotechnical parameters

Depth

σci (MPa)

mi

Ei (MPa)

GSI

c (MPa)

Φ (ο)

Upper marl

55

3.3

7

450

70

0.18

37

Middle marl

10

3.3

7

450

60

0.14

34

Lignite

5.70

5.3

20

380

75

0.25

53

Lower marl

30

3.3

7

450

60

0.14

34


The figure shows the layout of the pilot application of the room and pillar mining application
Figure. 2 Layout of the pilot application of the room and pillar mining at the Prosilio mine
The figure shows layout and roof bolting applications at the Prosilio mine.
Figure. 3 Main characteristics and layout of the roof bolting applied at the Prosilio coal mine


84 excavation stages including the complete layout, dimensions, and roof reinforcements, were defined in the program. Then, the main tunnel access entries (X1 and X2) were simultaneously excavated, followed by the stopes Y1-Y4 and Z1-Z2 (shown in Figure 4).

The figure shows different phases stopping activities modeled in RS3's finite element analysis.
Figure. 4 Different phases of the stopping activity as it was modeled in the FEA


What were their insights?

  • A good agreement was found between the results of the FEA analysis and the actual measurements of the mine (pillar loading, effective stress at different stages of excavations, etc.).
  • The finite element analysis showed maximum displacement values in the middle of the excavated rooms and the centre of the mine, ranging from 50 mm to 70 mm.
  • The roof displacements seemed to have lower values (40 mm) at the main access of rooms (X1 and X2) and the back of the mine (Y4).
  • Both FEA and field observation showed similar pillars deformation in three main axes.
  • Finite Element Analysis also confirmed that the overall stability of pillars and their responses to overburden loads were sufficient, which was verified by the actual performance of the pillars.
  • Failure in pillars were observed when less number of rock bolts were used in numerical modeling.
  • During the underground mining period, limited cracking was observed at the excavation’s corners as a result of local shear failures. Furthermore, at the main body of two pillars, a limited surficial spalling was observed, as it was seen in the 3D analysis at the yielded areas of the pillars.

Note: The figures below present the total displacement (Figures 5-8), strength factor and failure zones around the excavation (Figure 8) calculated by RS3.

The image shows displacement contours at the deformed cross sections in RS3's excavation model.
Figure 6. Displacement contours at the deformed X-X’ cross-section
The image shows total displacements in the coal pillars modeled in RS3
Figure 7. Total displacements in the coal pillars as derived from the FEA model
The image shows strength factor contours for the pillars of the mine modeled in RS3
Figure 8. Strength Factor contours at the central pillar and yielded elements (A – A’ cross-section)
The image shows the underground exploitation site after the completion of stoping activities.
Figure 9. View of the underground exploitation after the completion of the stoping activity

The takeaway from RS3’s Finite Element Analysis of Prosilio Underground Exploitation

RS3’s Finite Element Analysis (FEA) was helpful in evaluating the stability conditions of the Prosilio room and pillar pilot mining project. When combined with field observations, FEA reached a good agreement with the actual conditions of the underground exploitation by accurately capturing the excavation responses.

In conclusion, RS3 played an important role in helping engineers reduce the risk of structural failure and ensure a successful mine excavation while using an efficient mining method like the room and pillar approach.

For more details about this interesting project, read the complete paper.

Back to top

More from Rocscience