Search Results

6 - Leshchinsky Method and Tension Map Analysis

1.0 Introduction

This tutorial demonstrates the application of the Leshchinsky Method and Tension Map Analysis feature option in RSWall in conjunction with Slide2.

The analysis follows the procedure developed by Leshchinsky (2016; 2017) and adopted in AASHTO (2020; 2024) for determining the maximum tensile forces experienced in geosynthetic supports using a Limit Equilibrium Analysis (LEA).

The results of this tension map can be imported into RSWall for internal stability analysis, enabling the design and optimization of reinforcement layouts.

Before starting, it is recommended to complete RSWall Tutorial 1 – MSE Wall to become familiar with the basic wall modeling process.

This tutorial also requires Slide2 to perform an overall stability analysis. For more information, refer to the Tension Map help topics in both Slide2 and RSWall.

Topics Covered:

  • MSE Wall Design and Analysis
  • Geosynthetic Supports
  • Overall and Compound Stability analysis
  • Leshchinsky Method and Tension Map Analysis

Finished Product:

The final model for this tutorial is located in the Tutorial 6 folder. All tutorial files installed with RSWall can be accessed by selecting File > Recent Folders > Tutorials Folder from the RSWall main menu.

1.1 Background

According to AASHTO 2020/2024 Article 11.10.5.6, Limit equilibrium analyses (LEA) shall be used to evaluate compound stability for MSE walls, particularly those with complex geometry. Three analysis steps are to be conducted once an initial wall design is completed:

  1. Estimate nominal load in each reinforcement layer T_max using a load and resistance factor combination of 1.0.
  2. Adjust reinforcement design accordingly to meet limit states requirements with specified load factors.
  3. Check factored design using LEA with factored load and resistance values.

The procedure is based on the work of Leshchinsky et al. (2016, 2017) and implemented here using the Tension Map feature in Slide2.

The example in this tutorial is adapted from Example 1 in the 2016 FHWA report FHWA-HIF-17-004, Section 10.2, though results may differ due to variations in geometry, search methods, and calculation methods.

This methodology is stipulated only for AASHTO and for MSE walls with extensible reinforcement. Any other combination of model settings that do not satisfy these parameters will not be able to conduct a valid LEA and tension map analysis.

2.0 Getting Started

  1. Select File > Recent Folders > Tutorials Folders to open the tutorials folder.
  2. Select Tutorial 6 Tension Map – starting file.rswall and click Open.

3.0 Project Settings

  1. Select Home > Project > Project Settings project settings from the toolbar.
  2. Select the Design Standard tab and ensure the design standard is AASHTO (2020) and Extreme and Serviceability are deselected.
  3. Go to the Failure modes tab and, from the Internal Stability tab, deselect Crest toppling . We are mainly interested in reinforcement capacity.
  4. Select the Methodology tab and ensure the Active pressure method is Coulomb method and Tension in reinforcement is the Simplified method.
  5. Click OK to close the dialog.

Model

4.0 Soil properties

  1. Select Soil > Soil Conditions > Define Soil Properties Define soil properties in the toolbar.
  2. In the Define Soil Properties dialog, ensure the following soil properties are defined in the table below:
  3. Name

    Unit Weight (lbs/ft3)

    Friction Angle (o)

    Soil-Structure friction Angle (o)

    Long Term Cohesion (psf)

    Backfill

    120

    30

    15

    0

    Reinforced Soil

    125

    34

    17

    0

    Foundation

    110

    28

    14

    0

  4. Click OK to close the dialog.

5.0 Reinforcement Properties

  1. Go to the Loading and Support ribbon.
  2. Select Loading and Support > Reinforcement > Define Properties and ensure the reinforcement has the following properties in different tabs:

Strength

Allowable Tensile Strength (static)

2016.33 lbs/ft

Coverage

100%

Creep Factor

2.0086

Secant Stiffness

2016.33 (lbs/ft)

Soil Interaction

Interface sliding friction angle

28 degrees

Pullout Method

Coefficient of Interaction

Coefficient of Interaction

0.64

Alpha Coefficient

1.0

Connection

Connection function

Constant

Connection strength

3000 lbs/ft

The layout has already been added for convenience.

6.0 Compute and Export to Slide

  1. In the Results ribbon, select Results > Compute > Compute Compute in the toolbar.

results

When viewing results, we notice the governing CDR is the tensile strength of the bottom reinforcement, yielding a CDR of 1.22.

At this point, the RSWall model can be exported to Slide2 to check overall and compound stability, and then brought back into RSWall once computations are complete. Alternatively, the completed version of the Slide model can be found in File > Recent Folders > Tutorials Folder but it must be opened directly in Slide2.

Section 11.0 Slide2 Tension Map analysis (below) provides a step-by-step guide for modeling and analyzing the Slide2 file. However, a completed model file is also available for immediate use. In either case, ensure that the Slide2 model to be used for this tutorial has been fully completed and computed (Analysis > Compute). Results can be viewed in Analysis > Interpret. For this tutorial, it is only necessary to confirm that the computation has been successfully completed.

7.0 Import Tension Map Results into RSWall

Returning to the original RSWall file, we now import the completed slide model.

  1. In the Results ribbon, select Tension Map > Import from Slide2
  2. In the dialog, click Import and select the computed Slide2 file (if using the one provided, select Tension Map Analysis.slmd in the Tutorial 6 folder). Click Open.
  3. For Segment 1, select Segment 1 - Master Scenario - bishop simplified as the analysis.

Import from Slide2

The dialog allows you to assign a variety of results to any segment you wish. However, be aware that if at any point there are any import issues, such as missing data or a mismatch of support geometry, warnings will appear notifying you which segments could not find a match.

  1. Once assigned, ensure the checkbox for Compute results with tension map is selected and click OK. The segment(s) have now been assigned results from Slide2 and we can now recompute with this new data.
Because RSWall export results are a multi-scenario file types, these are currently the only Slide2 file type supported.
As mentioned, there are various verifications to ensure that the tension map data has been computed and is valid and compatible with the RSWall model. However, the verification does not check every possible aspect/feature of the model and a valid import does not guarantee that the models are 100% equivalent. Ensure that both models are modeled as intended and that assignment of results is correct.

8.0 Recomputing with LEA results

  1. In the Results ribbon, select Compute > Compute compute in the toolbar.

results with tension

The tensile forces imported from Slide2’s Tension Map Analysis fall between the higher demands observed near the bottom of the wall and the lower forces at the very top. Notably, the top reinforcement now shows a capacity–demand ratio (CDR) below 1.0 for pullout, indicating insufficient pullout resistance for the force required by the compound stability analysis to maintain a factor of safety of 1.0. Although tensile failure often governs the design, in this case the required tensile force exceeds the available pullout capacity. As a result, a redesign of the reinforcement configuration, such as increasing reinforcement length, reducing spacing, or selecting stronger materials, may be necessary.

The redesign may vary depending on user preferences, engineering limitations, material, etc. and may require iteration between Slide2 and RSWall in order to achieve a stabilized wall.

9.0 Summary

This tutorial demonstrated the use of Tension Map analysis tool from Slide2 to perform both overall and compound stability checks, helping verify whether the internal reinforcement design is adequate. While this example focused on adjusting the tensile strength of the supports, it is important to recognize that this is only one of several possible redesign strategies. Other approaches may include increasing the reinforcement length, reducing spacing, or adding additional layers, depending on the model conditions and engineering constraints.

Lastly, the information provided by the tension map is used in a compound stability analysis as outlined in AASHTO for RSWall. In this scenario, the unfactored tensile forces determined using the tension map results are imported into RSWall and factored as the new maximum tensions to ensure internal stability design continues to be sufficient provided the new results from an overall stability analysis. A final overall stability analysis with applied factors may also be required to verify overall stability.

10.0 References

Leshchinsky, D., Kang, B., Han, J., Ling, H., Framework for Limit State Design of Geosynthetic-Reinforced Walls and Slopes, Transportation Infrastructure Geotechnology, March 2014, pp 129-164.

Leshchinsky, D., Leshchinsky, B., Leshchinsky, O., Limit state design framework for geosynthetic-reinforced soil structures, Geotextiles and Geomembrances, August 2017, pp 642-652.

Leshchinsky, D.,Leshchinsky, O., Zelenko, B., Horne, J., Limit Equilibrium Design Framework for MSE Structures with Extensible Reinforcement, Federal Highway Administration, October 2016.

11.0 Slide2 Tension Map Analysis

As mentioned above, this section outlines the steps for creating and analyzing tension map results in Slide2. For more information, see the Slide2 Tension Map help topic.

11.1 Slide2 Model

  1. In RSWall, select Results > Export > Export to Slide2
  2. Select Segment 1.
  3. Click Open in Slide2. The Slide2 program will launch.
  4. Select the location to save the Slide2 file, enter the name Tutorial 6 - Tension Map Analysis and click Save.

11.1.1 Project Settings

  1. Select Analysis > Project Settings project settings
  2. Go to the Methods tab and ensure Bishop and GLE are selected and Janbu is deselected.
  3. Click OK to close the dialog.

project settings

11.1.2 Material Properties

  1. In the Segment 1 scenario, select Properties > Define Materials and ensure the below materials have the following properties:

Name

Cohesion (psf)

Phi (degrees)

Unit Weight (lbs/ft3)

Backfill

0

30

120

Reinforced Soil

0

34

125

Foundation

0

28

110

Define Mateial Properties dialog

11.1.3 Slope Limits

  1. Right-click on the existing slope limit and select Define Limits (or select Surfaces > Slope Limits > Define Limits).
  2. Check the box for Second set of Limits and ensure the coordinates are set to the following:

Limits

Left x coordinate

-25

Right x coordinate

2.67

Second set of limits

Left x coordinate

2.67

Right x coordinate

52.67

Define limits dialog

  1. Alternatively, move the second slope limits such that they are at the top-left corner of the reinforce soil material such that they look like the following:

Model with limits defined

11.2 Define Support Properties

  1. Select Properties > Define Support
  2. Select the Reinforcement 1 support and ensure the support type is a geosynthetic with the following properties:

General

Force Application

Active (Method A)

Force Orientation

Parallel to reinforcement

Strip Coverage

100%

Allowable Tensile Strength

100 lbs/ft

Pullout and Stripping

Anchorage

Slope Face

Connection Strength Input

Constant

Connection Strength

3000 lbs/ft

Input Type

Coefficient of Interaction

Coefficient of Interaction

0.64

Material Dependent

No

Use external loads in strength computation

Yes

The high connection strength and anchorage at both ends is meant to ensure that failure will not occur with stripping or pullout for the purposes of this example. It is important to note that the allowable tensile strength does not affect the tension map results but will continue to run a separate LEM analysis. We can use this to our advantage when we redesign the support.

11.3 Setting up the analysis

11.3.1 Surface Options

Although the original example uses Bishop’s method with log-spiral shaped surfaces, we will use a circular surface type and the Auto Refine Search method.

  1. Select Surfaces > Surface Options.
  2. To achieve a thorough search, we change the Search Method options by clicking Options and changing the settings to the following:

Divisions Along Slope

40

Circles per Division

20

Number of Iteration

20

Divisions to use in next iteration

75

  1. In the Filters option, set a minimum area of 20 ft2 in order to eliminate small, irregular surfaces due to the cohesionless material. Ensure the checkbox is selected.

Surface Filters

surface options dialog

  1. Click OK twice to close both dialogs.

11.3.2 Tension Map Settings

  1. Go to Support > Tension Map
  2. Select the Compute reinforcements tension map checkbox and ensure the Target factor of safety is 1.0 and click OK.

Tension Map dialog

As per the footnote in this dialog, only horizontal geosynthetics will work as the method developed by Leshchinsky assumes horizontal reinforcement that provides strength due to extension.

11.4 Computation and Interpretation

  1. Run the analysis by selecting Analysis > Compute compute button
  2. When computations are done, open the Interpreter by selecting Analysis > Interpret Interpret icon

When viewing the results, we can see that a failure is occurring within the reinforced zone, indicating the reinforcement strength is insufficient. Furthermore, when we select Data > Show Support Force Diagram we notice that the tensile strength is still the governing failure mode for the global minimum surface.

Show support force diagram

While iteration can be used, the tension map results can provide insight into how one might redesign support tensile strength to ensure a sufficient factor of safety.

When we select Data > Show Support Tension Map, we notice that the maximum tension experienced by the supports is approximately 715 lb/ft for Bishop and approximately 575 lb/ft for GLE.

Tension Map Results for Bishop
Tension Map Results for Bishop simplified
Tension Map Results for GLE
Tension Map Results for GLE

From these results, we learn the following.

  • The tensile forces are similar to the original example but far exceeds our current tensile strength. A redesign is required to ensure the wall isn’t failing.
  • It is important to consider other slope methods including ones considering full equilibrium such as GLE, as there may be a significantly different tension map result that results in a different final design.

We will redesign the support strength for the Bishop case.

11.5 Support Redesign

  1. Return to the modeler and open Support Properties once again (select Properties > Define Support).
  2. In the circular scenario, change the Allowable Tensile Strength of the Geosynthetic Reinforcement to 1000 lbs/ft after accounting for the factored tensile strength.

11.6 Computation and Interpretation (After Redesign)

  1. Run the analysis (Analysis > Compute) and open the Interpreter (Analysis > Interpret) when computations are done.

For the circular scenario and Bishop, the new redesign essentially achieves the FS of 1.0 initially specified. Thus, we can confirm that the tensions are the maximum tensions the support can expect.

Tension map results

11.7 Non-circular Analysis

It is important to consider a non-circular analysis which often provides a lower factor of safety and surface shape and thus a different required tensile force. Furthermore, both the slope and searching method also play a part in determining a solution.

For example, the following tension map analysis uses a non-circular analysis using GLE method and Particle Swarm Optimization (PSO). We find that the tensile force is different compared to the circular analysis results. As such, it is important to consider non-circular searching in order to verify the stability of the wall.

Noncircular analysis with tension map

While a powerful tool, there are some specific limitations of this analysis. It’s possible after redesigning the support, originally invalid surfaces now converge which ultimately changes the final tension map results. This is due to the nature of the algorithm that optimizes based on where the minimum factor of safety has been found for the current model, an inherent attribute in PSO and surface altering. As such, tension map discrepancies may be more visible with more comprehensive searches or slope methods that do not consider complete equilibrium. In this case, further iteration and design may be required to find the maximum tensions required to stabilize the slope.

Rocscience logo, click here to return to the homepage Portal Account Portal Account Log In Log Out Home Shopping Cart icon Click here to search our site Click here to close Learning Tech Support Documentation Info Chevron Delete Back to Top View More" Previous Next Edit PDF File Calendar Location Language External Link Apply to ACC External Link Fees Video Click here to visit Rocscience's LinkedIn page Click here to visit Rocscience's YouTube page Click here to visit Rocscience's X page Click here to visit Rocscience's Facebook page Click here to visit Rocscience's Instagram page Click here to visit Rocscience's Reddit page Bookmark Network Scroll down for more Checkmark Download Print Back to top Single User Multiple Users RSLog RocFall3 CPillar Dips EX3 RocFall RocPlane RocSlope3 RocSupport RocTopple RS2 RS3 RSData RSPile RSWall RSSeismic Settle3 Slide2 Slide3 SWedge UnWedge RocTunnel3 RocSlope2 BlastMetrix ShapeMetriX FragMetriX TestLicense Commercial License Education License Trial License Shop safe & secure Money-back guarantee