Copy Loads

The Copy Load option can be used to create copies of loads or excavations.

To use Copy Load:

  1. Select Copy from the toolbar or the Edit sub-menu of the Loads menu.

  2. In the Plan View, use the mouse to select the loads / excavations you would like to copy.

  3. When you are finished selecting, press Enter or right-click and select Done Selection.

  4. You will then be prompted to enter two points defining the location of the copied load(s), relative to the original load(s). You can enter the points graphically with the mouse, or with the keyboard in the prompt line (see notes for additional information).

  5. After the second point is entered, all of the loads/excavations selected in Step 2 will be copied to the new location, according to the vector defined by the two points.

NOTE:

Right Click Shortcut

Copy Load is also available as a right-click option for individual loads/excavations:

  1. In the Plan View, click the right mouse button on a load or excavation, and the boundary will be "selected".

  2. A popup menu will appear, from which you can select the Copy option.

  3. Select Copy and complete steps 4 and 5 described above.